How do you calculate a machine hour rate?
Part 1 of 9 in the series Costing and quoting
Short answer
A machine hour rate is the yearly cost of one machine divided by its productive hours. Add up depreciation, interest, maintenance, tooling, floor space, energy, insurance and software, then divide by the hours it runs on orders. Put the operator beside it as a separate rate, and you have a manned and an unmanned rate.
On this page
What is a machine hour rate?
A machine hour rate is what one hour on a particular machine costs your shop. You add up that machine's costs over a year and divide them by the hours it is occupied by orders.
The hourly rate belongs to the cost price of a part. The selling price is that cost price with your margin on top. The owner sets that margin per customer, material or risk. If profit is already built into the rate, the quote counts it twice.
Work out a rate per machine rather than one average for the whole business. A new 5-axis machine costs something different per hour from an old 3-axis one; one average makes work on the big machine too cheap and work on the small one too dear. An ACCA technical article grants that one absorption rate for all overheads is quick and easy, but warns that it is probably too simple.
Record each rate once in your machine registry, so everyone who prices work uses the same figure. How that rate then lands in a cost formula is shown in Excel estimating.
What costs go into a machine hour rate?
These items belong in the rate of a machining centre or lathe. Most come straight from your books: the purchase from the fixed asset register, the rest from last year's cost accounts.
Depreciation for pricing need not match the figure in your annual accounts. Tax rules set their own limits: the Dutch tax authority, for instance, caps depreciation at 20 per cent of the purchase cost a year and lets you use the economic life where it is shorter than the technical one. For the rate, choose the years in which the machine has to earn its money back.
The operator's wage is deliberately missing; it gets a rate of its own.
- Depreciation: purchase price minus residual value, divided by the useful life in years.
- Interest on the average capital employed: with straight-line depreciation, on average half of purchase price plus residual value is tied up in the machine. That half times the interest rate is the yearly interest item.
- Maintenance: servicing, repairs and spare parts.
- Tooling and coolant for general use; special tooling for a single order belongs to that order.
- Floor space: the share of rent or building costs for the machine's footprint, including room to operate it and to set down raw and finished parts.
- Energy: power for the machine, extraction and compressed air.
- Insurance of the machine.
- Software that goes with the machine, such as licences and updates.
How many productive hours should you divide by?
The divisor shapes the rate as much as the costs do. Productive hours are the hours the machine is taken up by an order: setting up, cutting, measuring the first article. Maintenance, breakdowns and hours without work do not count. Divide by hours the machine never runs and the rate comes out too low, along with every price built on it.
The German guideline VDI 3258 Part 1, as the publisher Haufe summarises it, makes that divisor concrete. Start from the running time a year theoretically allows and take off standstill and maintenance. Standstill has three parts: days without work, the hours of a working day left idle when you run one or two shifts, and a percentage from experience for stoppages caused by operations or production.
A formula taught in Dutch business economics splits the costs. Fixed costs such as depreciation, interest, floor space and insurance go over the normal number of machine hours; variable costs such as energy, tooling and part of the maintenance go over the hours budgeted for this year. A quiet year then does not push the rate up: the empty hours show as under-recovery in your own figures, not as a higher price for the customer.
If the machine also runs unattended, say in the evening on a batch that runs stably, those hours count too. The difference between manned and unmanned hours lies in the operator beside the machine. The machine rate itself stays the same.
A worked example: from €77,000 to €35 an hour
An example with round numbers: take a milling machine of €400,000, depreciated over 10 years with no residual value, and 5 per cent interest on the average capital employed. With the items from the list, that comes to a yearly total of €77,000.
Divide that €77,000 by 2,200 productive hours and the machine rate is €35 an hour. In this example the 2,200 hours are one day shift plus some unattended hours in the evening.
Now put an example operator rate of €50 beside it. A manned hour then costs €85 and an unmanned hour €35. Charge €85 for every hour and the unattended evening hours come out €50 too dear. Charge €35 for every hour and the operator vanishes from the price.
| Cost item | Per year |
|---|---|
| Depreciation (€400,000 over 10 years) | €40,000 |
| Interest (5 per cent on an average €200,000) | €10,000 |
| Maintenance | €8,000 |
| Tooling and coolant | €7,000 |
| Floor space | €5,000 |
| Energy | €4,000 |
| Software | €2,000 |
| Insurance | €1,000 |
| Total per year | €77,000 |
Does labour belong inside the machine rate?
A rate with the operator built in is common practice. It works as long as every hour is manned and each machine has its own operator.
Subduxion keeps machine and labour apart, as two rates. Manned or unmanned is then not a factor on a single rate: a manned hour is machine plus operator, an unmanned hour is the machine alone. Labour is never counted twice that way, not even when one operator walks between two machines.
If one operator runs two machines at once, split the operator's rate across both: in the example, €25 of labour per machine hour instead of €50. Build the operator rate from gross wage, employer's costs and the hours someone actually spends at the machine.
Which hours go at which rate?
An order occupies the machine even when no chips are flying. While it is being set up the spindle mostly stands still, but the machine is committed to that order and the operator is at it. Setup time goes at the manned rate. How the number of setups drives that time is covered in counting setups.
Cycle time goes at the manned rate when someone is at the machine and at the unmanned rate when the batch runs unsupervised. Programming time belongs to the programmer, at their own rate, unless the programming happens at the control and the machine is occupied all that time.
Put each time on its own estimate line, with time, rate and quantity beside it. The quote then shows where the money sits: in setting up and programming for a small batch, in cycle time for a large one. How that split shifts with quantity is the subject of why a small batch costs so much per part.
What do you do with a fully depreciated machine?
After 10 years the example machine stands at zero in the books, and €40,000 of depreciation drops out of the yearly total. Take the depreciation from the books and that item disappears from the rate and from every quote on that machine, while its successor still has to be paid for out of the same hours. Your ERP and your accounts record what the machine cost. What it still has to earn is a decision for the shop, and that decision belongs in the rate.
Two choices hold up. You keep charging depreciation on the replacement value, so the rate saves for the next machine. The German method Haufe describes has that variant: depreciation per machine hour is then the replacement value divided by the useful life in years times the running hours per year. Or you drop the depreciation on work where you want to bring the price down; that is then a pricing decision, not a lower cost price.
An older machine sometimes takes longer over the same part. A lower rate on a machine that runs twice as long can make that part more expensive. Compare the cost per part, not the rate per hour.
Review the rates once a year: energy, rent and maintenance move, and last year's productive hours are a sound starting point for this year's divisor. The post-calculation shows whether the booked hours match the budget; estimate and actual per operation covers that.
In Blake
In Blake you record each machine once in the machine registry, with its envelope, axes and your own hourly rate. The cost engineer prices a part on a machine from that registry, at its own rate, instead of an average from a spreadsheet. If the machine does not fit, a first check on envelope and axes shows which limit decides. Material, machining, setup and programming sit on separate lines, per piece and per batch, each with time, rate and quantity. You can check the cost price at every quantity break, and the whole team prices with the same machines and rates.
Frequently asked questions
What is included in a machine hour rate?
Every yearly cost of that one machine: what the capital costs (depreciation and interest), what it consumes (maintenance, tooling, coolant, energy) and what comes with it (floor space, insurance, software). The operator's wage and special tooling for a single order stay out; price them separately.
How many productive hours per year should you use for a CNC machine?
The hours the machine is occupied by orders, unattended hours included. The German VDI guideline for machine hour rates starts from the theoretical time in a year and subtracts non-working days, shifts you do not run, stoppages and maintenance. Your shift pattern sets the divisor.
Should labour be included in the machine hour rate?
Keep it separate. With a machine rate and an operator rate, a manned hour is the sum of both and an unmanned hour is the machine alone. Labour is then never counted twice, even when one operator runs several machines.
Is the hourly rate for a five-axis machine higher?
Yes, if the machine costs more and runs the same productive hours: depreciation, interest and maintenance are higher. Setups decide whether the part costs more. What fits one setup on a five-axis machine often takes more setups, and more setup time, on a three-axis one.
Should a fully depreciated machine get a lower rate?
Not by default. The books have finished depreciating it, but the machine will need replacing. Keep charging on replacement value and the rate saves for its successor. Drop the depreciation and you have made a pricing decision.
Does the machine hour rate tell you the cost per part?
Only together with time. The machine share of the cost per part is the rate times the time per part, plus setup time spread over the batch. A lower rate on a slower machine can still cost more per part, so compare per part.
Sources
- Belastingdienst (Netherlands Tax Administration), Hoe berekent u het bedrag van de afschrijving?, consulted November 2026 (opens in a new tab)
- Ken Garrett, ACCA, Activity-based costing (Performance Management technical article), consulted November 2026 (opens in a new tab)
- Walter Schanz, Haufe, Maschinenstundensatzrechnung: 5 So gehen Sie bei der Maschinenstundensatzrechnung vor (VDI 3258 Part 1), consulted November 2026 (opens in a new tab)